The hold one minute is to complete the segment.
Segment = RAMP, TEMP, HOLD
on the last segment, if you put 0 "zero" for the hold time, then the segment will be incomplete and the controler wont run that segment. That would be bad news, because the contoler would then turn off the kiln at the end of the previous segment.
Feel free to pm me with questions.... on any kiln or controler, annealing, fusing or casting.
Ron